Finishing Up For 2016

I return to Guanajuato for the winter on November 1.  The garage construction will be *mostly* complete.  Next year I will install the soffits and touch-up the paint.  I may not get the garage doors done this year either.

I´ve been working on the cedar siding.  It goes on quickly but the painting before hand takes time.  I have one wall remaining to do.

On the inside I have three walls covered with plywood and have just started the ceiling.  I had to figure out how to (safely) raise and nail the plywood sheets by myself.  So far so good but nailing upside-down is tiring.

Over The Hump

Today I leave to travel to Ontario to visit family and will return at the end of August.  Last Friday the garage passed its framing inspection and yesterday the first electrical inspection.  My priority now is to finished the exterior before returning to Mexico for the winter.